Najrab district’s road construction reaches 24% physical progress

Kapisa: The construction of the road in the Najrab district of Kapisa province in four sections (Hood, Jorghal, Kharaj, and Ghacholan) is under construction by the Ministry of Public Works.

According to the Ministry of Public Works, the construction works of this project have 24.5 percent progress so far.

This road is more than 15 kilometers long and 6.6 m wide, which has been included two piers of RCC bridges with a length of 30 and 70 meters each, and some 119 numbers of culverts and ditches.

With the completion of this road project, several districts of Kapisa province will be connected with each other’s, and it will lead to huge positive changes in the agricultural, economic and social sectors.

MoPW Media Team – Kabul

9 months 3 weeks ago

.

تازه ترین اخبار

چهارشنبه ۱۴۰۵/۳/۲۷ - ۱۳:۵۸
Background image

وزیر فواید عامه ازجریان کار قطعه چهارم خط‌آهن خواف- هرات بازدید کرد

محترم الحاج ملا محمد عیسی ثانی، وزیر فواید عامه‌ا.ا.ا، در ادامه‌ی سفر کاری خود به ولایات زون جنوب‌غرب کشور، پس از بازدید و ارزیابی شماری از پروژه‌های زیربنایی درین ولایات، به ولایت هرات. . .

چهارشنبه ۱۴۰۵/۳/۲۷ - ۱۳:۱۶
Background image

کار قیرریزی سرک جلال‌آباد – تورخم آغاز و عملاً جریان دارد

کار اعمار اساسی لین دوم شاهراه جلال‌آباد – تورخم از سوی وزارت فواید عامه ا.ا.ا با سکتور خصوصی قرارداد شده بود که اکنون عملاً جریان دارد.

این پروژه ۷۳ کیلومتر طول دارد و کار بخش‌های. . .

سه‌شنبه ۱۴۰۵/۳/۲۶ - ۱۵:۸
Background image

وزیر محترم فواید عامه از جریان کار اعمار سرک میل ۷۸ ابونصر فراهی بازدید کرد

محترم الحاج ملا محمد عیسی ثانی وزیر فواید عامه ا.ا.ا، در ادامه سفر کاری خویش به زون جنوب‌غرب کشور، در حالیکه وی را یک تیم تخنیکی همراهی می نماید، از جریان کار اعمار سرک میل ۷۸ – ابونصر. . .

BACK TO NEWS