Daikundi: The urban roads of Nili City reach 73% progress

Anonymous (not verified)
سه‌شنبه ۱۴۰۰/۵/۵ - ۱۳:۹
Daikundi: The urban roads of Nili City reach 73% progress

The 8.8 km long and 14 meters wide urban roads project in Nili city, the capital of Daikundi province, is underway and has reached 73% of physical progress, so far.

According to the Ministry of Public Works, the contract of this project was signed with a private construction company, which valued more than 631 million Afghanis and was funded by the Afghan government.

The implementation of this project was the main demand of the people of Daikundi province. With the completion of this project, in addition to reducing traffic congestion and air pollution inside the city; indeed, it will also reduce the transport costs and waste of time.

MoPW Media Team - Kabul

11 months 4 weeks ago

.

تازه ترین اخبار

دوشنبه ۱۴۰۵/۶/۲ - ۱۲:۳۶
Background image

کار ترمیم و بازسازی ۱۷ کیلومتر سرک مسیر عمومی گردیز – خوست آغاز شد

کار ترمیم و بازسازی ۱۷ کیلومتر سرک مسیر عمومی گردیز – خوست که به ارزش ۱۲۲ میلیون و ۳۹۸ هزار افغانی میان وزارت فواید عامه ا.ا.ا و سکتور خصوصی قرارداد شده بود، که روز گذشته با حضور محترم. . .

یکشنبه ۱۴۰۵/۶/۱ - ۱۴:۵۰
Background image

معینیت خط آهن وزارت فواید عامه به‌عنوان یک اداره مستقل از این وزارت جدا و رئیس جدید آن معرفی گردید

بر اساس حکم عالیقدر امیرالمؤمنین حفظه‌الله تعالی، معینیت خط آهن وزارت فواید عامه به‌عنوان یک اداره مستقل از این وزارت جدا شد و بر اساس همین حکم، محترم الحاج مولوی عبد الکریم فاتح، که. . .

یکشنبه ۱۴۰۵/۶/۱ - ۸:۴۱
Background image

کار بازسازی شاهراه سالنگ ها به شدت جریان دارد

محترم الحاج ملا محمد عیسی ثانی، وزیر فواید عامه ا.ا.ا، در ادامه سفر کاری خود به ولایت‌های شمال کشور، در حالی که یک تیم تخنیکی نیز وی را همراهی می‌نمود، از جریان کار پروژه بازسازی اساسی. . .

BACK TO NEWS