Najrab district’s road construction reaches 24% physical progress

ناپیژنده (not verified)
سه‌شنبه ۱۴۰۰/۴/۱ - ۱۵:۱۷
Najrab district’s road construction reaches 24% physical progress

Kapisa: The construction of the road in the Najrab district of Kapisa province in four sections (Hood, Jorghal, Kharaj, and Ghacholan) is under construction by the Ministry of Public Works.

According to the Ministry of Public Works, the construction works of this project have 24.5 percent progress so far.

This road is more than 15 kilometers long and 6.6 m wide, which has been included two piers of RCC bridges with a length of 30 and 70 meters each, and some 119 numbers of culverts and ditches.

With the completion of this road project, several districts of Kapisa province will be connected with each other’s, and it will lead to huge positive changes in the agricultural, economic and social sectors.

MoPW Media Team – Kabul

...

8 میاشتې ago

...

تازه خبرونه

شنبه ۱۴۰۵/۲/۵ - ۱۴:۳۲
Background image

د جلال‌آباد - تورخم د دویم لین سړک د پاتې برخو د رغنیزو چارو بیا پیل او له یادې پروژې څخه د ټولګټو وزارت د محترم وزیر لیدنه

د جلال‌آباد - تورخم د دویم لین سړک د پاتې برخو رغنیزې چارې بیا پیل شوې، چې له یادې پروژې څخه د ا.ا.ا د ټولګټو وزارت محترم وزیر، الحاج ملا محمد عیسی ثاني، له نږدې لیدنه وکړه او د پروژې. . .

پنجشنبه ۱۴۰۵/۲/۳ - ۱۲:۴۸
Background image

په هلمند ولایت کې د ګرشک – موسی‌قلعه مسیر د دویمې برخې ۲۶.۵ کیلومتره سړک د اساسي رغونې چارې روانې دي

د ا.ا.ا د ټولګټو وزارت د هېوادوالو د ترانسپورتي ستونزو د حل په موخه، د هلمند ولایت د ګرشک – موسی‌قلعه مسیر د دویمې برخې ۲۶.۵ کیلومتره نښلوونکي سړک د اساسي رغونې چارې پیل کړې دي، چې دا. . .

چهارشنبه ۱۴۰۵/۲/۲ - ۹:۲۶
Background image

د مزار شریف – دره صوف ۵۶.۳ کیلومتره سړک د اساسي بیا رغونې چارې ۵۱ سلنه بشپړې شوې دي

د ا.ا.ا د ټولګټو وزارت له لوري د مزار شریف – دره صوف ۵۶.۳ کیلومتره سړک د اساسي بیا رغونې چارې د ۱۵۹ میلیون افغانیو په لګښت تېر کال پيل شوې وې چې دا مهال ۵۱ سلنه بشپړې شوې دي.

د. . .

BACK TO NEWS