Najrab district’s road construction reaches 24% physical progress

Anonymous (not verified)
سه‌شنبه ۱۴۰۰/۴/۱ - ۱۵:۱۷
Najrab district’s road construction reaches 24% physical progress

Kapisa: The construction of the road in the Najrab district of Kapisa province in four sections (Hood, Jorghal, Kharaj, and Ghacholan) is under construction by the Ministry of Public Works.

According to the Ministry of Public Works, the construction works of this project have 24.5 percent progress so far.

This road is more than 15 kilometers long and 6.6 m wide, which has been included two piers of RCC bridges with a length of 30 and 70 meters each, and some 119 numbers of culverts and ditches.

With the completion of this road project, several districts of Kapisa province will be connected with each other’s, and it will lead to huge positive changes in the agricultural, economic and social sectors.

MoPW Media Team – Kabul

8 months 1 week ago

.

تازه ترین اخبار

پنجشنبه ۱۴۰۵/۲/۱۰ - ۱۱:۳۶
Background image

در ماه حمل از طریق خطوط آهن ۸۷۳۹۸۱ متریک تُن انتقالات صورت گرفته است

از آغاز الی ختم ماه حمل سال ۱۴۰۵هـ.ش. از طریق خطوط آهن وزارت فواید عامه افغانستان ۸۷۳۹۸۱ متریک تُن انتقالات صورت گرفته است.

در این میان از طریق بندر حیرتان ۵۷۷۹۸۹  تُن، بندر آقینه ۸۲۹. . .

چهارشنبه ۱۴۰۵/۲/۹ - ۱۵:۴۶
Background image

کار اعمار و احداث سرک پنجشیر_تخار به طول ۲۵ کیلومتر و با ارزش بیش از ۴۵۱.۶ میلیون افغانی آغاز شد

وزارت فواید عامه، بر اساس پالیسی اقتصاد محور ا.ا.ا، کار اعمار و احداث سرک پنجشیر_تخار را به ارزش بیش از ۴۵۱.۶  میلیون افغانی با سکتور خصوصی قرارداد نموده که امروز با حضور محترم الحاج. . .

چهارشنبه ۱۴۰۵/۲/۹ - ۱۵:۱۳
Background image

کار اعمار سرک ولسوالی خوگیانی‌ ولایت غزنی به طول ۲۵ کیلومتر به ارزش ۷۵۷ میلیون افغانی آغاز شد

کاراعمار اساسی سرک ولسوالی خوگیانی‌ ولایت غزنی به ارزش ۷۵۷ میلیون افغانی میان وزارت فوایدعامه و سکتور خصوصی قرارداد شده است و امروز با حضور داشت محترم الحاج مولوی سردار محمد مدنی معاون. . .

BACK TO NEWS